Case study
Location: London
Client: Essential Living
Main contractor: McLaren
Contract value: £6.3M
Programme: 12 months
Archway Tower
Brief
To provide 118 new residential units with communal living space and a basement energy centre. All of which achieved BREAAM “Excellent” standard.
Scope of services
- Electrical and mechanical infrastructure to supply 118 new apartments.
- On site energy centre with 4no gas fired boilers.
- On site emergency standby 275Kva generator.
- High pressure water mist system.
- New electrical switchgear and rising busbar throughout.
- Intelligent lighting control systems and LED lighting throughout.
- Fibre optic data transmission system.
- Multi-discipline TV/IRS distribution system
Get in touch with Gloster MEP.
Call: 0207 089 6910
Email: enquiries@glostermep.co.uk