Case study

Location: 1 Stockley Park

Client: CBRE Investors

Main contractor: ISG

Consultant: The Anslow Partnership

Contract value: £1.7M

Programme: 34 weeks

Stockley Park

Brief

A mechanical Cat A fit-out, which comprised of complete mechanical, public health, and BMS systems prior to a Cat B fit-out.

Scope of services

  • 2No 5.0m3/h heat recovery AHUs and 2No 500 kw air cooled chiller.
  • 2No Packaged plant rooms prefabricated off site and assembled in situ, including boilers and pump skids.
  • 220No 4-pipe FCU with trend IQ controls.
  • 4No new toilet areas with plumbing and ventilation services.

Solution

Due to the short programme available, a detailed coordination exercise was carried out to allow the plant rooms to be prefabricated off site, before being crane lifted into position.