Programme: 30 weeks

Schroders – Project Denim

Brief

The Holmwood House office block consists of a basement, ground and two floor office accommodation, as well as a 2nd-floor plant room. Remodelling was to be completed on all floors and plant to be relocated.

Scope of services

  • Complete replacement and relocation of plantroom.
  • Complete replacement of electrical and mechanical services to supply four floors of commercial office infrastructure.
  • Three 87kW boilers and direct hot water cylinders with a plate heat exchanger.
  • Intelligent lighting control systems throughout all floors.
  • New LV panels.
  • Installation of rising busbar.
  • New 11kV sub-station.
  • New full-load generator system.
  • New MER and SER rooms throughout.

Solution

A commercial office use refurbishment in Horsham, West Sussex. Electrical and mechanical commercial office infrastructure was provided to supply a full Cat A and Cat B fit-out over 4 floors. Designed to improve function and energy efficiency.